LIST OF TOPICS TO BE DISCUSSED
· Review and approve agenda
· Review and approve minutes from 1/19/22 and 2/8 Joint SB meeting
· Review and discuss feedback from SB review of Summary of Findings document at 2/8 SB Mtg
· Discussion of potential paths forward
· Public Questions and Comments
· UPCOMING MEETINGS MEETING/EVENT EST. TIME LOCATION
· Mar 16th, 2023 Regular Meeting 10:00 am Zoom
Abbreviations:
RC Richard Chase
RB Richy Bisk
BK Brian Keevan
JG Jennifer Greene
CBH Corey Burnham-Howard
JM John Mirick
SP Sherry Patch
HT Helen Townsend
TL Terri Longtine
HL Helga Lyons BH Bonnie Hirsh LG Larry Greene VT Victoria Taft
Virtual Meeting Instructions:
Richard Chase is inviting you to a scheduled Zoom meeting.
Topic: Princeton Solar Farm Working Group
Time: Mar 16, 2023 10:00 AM Eastern Time (US and Canada)
Join Zoom Meeting
https://us02web.zoom.us/j/87337119825?pwd=MHM3andXUHhVZm5IODdYRWRCWUtNQT09
Meeting ID: 873 3711 9825
Passcode: 236235
One tap mobile
+13126266799,,87337119825#,,,,*236235# US (Chicago)
+16465588656,,87337119825#,,,,*236235# US (New York)
Meeting ID: 873 3711 9825
Passcode: 236235
Find your local number: https://us02web.zoom.us/u/kd67xdmyya
Items for Project:
Can DCR land be incorporated into project scope, Not for phase 1 due to timing
· Lease issues
· Article 97 required, potentially yes.
Post Closure Use Permit
· How much can PSF, Town and PMLD do to minimize consultant costs. PSF to do as much as possible on a volunteer basis
· Feasibility Study preparation by PSF with input from Town/ PMLD
Town vs PMLD roles
· ATM warrant article draft
· Who is to issue the RFP (Town)
PMLD
· Nextera Contract implications
· Interconnection implications
RFP process
DCR land research update Acres Percent
· Commonwealth of Mass 3929 17.12%
· DCR 3348 14.59%