Updated Coal Kiln Road Closure Schedule - Beginning 7/25/2022

As noted, beginning Monday, July 25th, 2022, Coal Kiln Road will be closed to thru-traffic for a road reconstruction project. Below you will find an anticipated timeline for this project (please note this is subject to change due to weather etc.)

Erosion Control: 7/18 – 7/22
Reclaim and Grade: 7/25 – 7/29
Pave Binder: 8/1 – 8/5
Pave Berm: 8/10
Pave Top: 8/22 – 8/24

Please forward questions to Department of Public Works Superintendent Benjamin Metcalf by calling 978-464-2120 or emailing highway@town.princeton.ma.us. We are sorry for any inconvenience this may cause.

Thank you